TM 5-3895-379-23-1
FIELD MAINTENANCE
COOLANT SYSTEM PRESSURE TEST
INITIAL SETUP:
Personnel Required
Tools and Special Tools
Construction Equipment Repairer 91L
Tool Kit, General Mechanic's: Automotive
(Volume 2, WP 0289, Table 1, Item 39)
Gloves, Rubber
References
(Volume 2, WP 0289, Table 1, Item 12)
TM 5-3895-379-23P, Figure 37
Goggles (Volume 2, WP 0289, Table 1, Item 13)
Indicator, Point Set, Group
(Volume 2, WP 0289, Table 1, Item 16)
Equipment Condition
Pan, Drain, 5 Gal Cap.
Engine off. (TM 5-3895-379-10)
(Volume 2, WP 0289, Table 1, Item 23)
Drums chocked. (TM 5-3895-379-10)
Pump, GP Cool SYS
Right-side door assembly opened.
(Volume 2, WP 0289, Table 1, Item 28)
(TM 5-3895-379-10)
Resistor, Thermal
(Volume 2, WP 0289, Table 1, Item 30)
0135-1
03/15/2011Rel(1.8)root(maintwp)wpno(M00073)