TM 5-3895-379-23-1
0199
INSTALLATION - Continued
19.
Install three new lockwashers (Figure 23, Item 3), wires (Figure 23, Items 4, 5, and 10), and nuts
(Figure 23, Item 1) on VPM tachometer terminals (Figure 23, Items 2, 8, and 9).
20.
Install lamp assembly (Figure 23, Item 6) in VPM tachometer (Figure 23, Item 7).
2
1
3
1
10
4
3
1
5
9
8
3
6
7
M0347SWR
Figure 23. Instrument Wiring Harness Installation.
21.
Carefully position instrument box assembly (Figure 24, Item 6) and instrument wiring harness assembly
(Figure 24, Item 4) on operator station (Figure 24, Item 11).
22.
Connect connector (Figure 24, Item 1) to connector (Figure 24, Item 14).
23.
Connect connector (Figure 24, Item 2) to connector (Figure 24, Item 13).
24.
Connect connector (Figure 24, Item 15) to connector (Figure 24, Item 16).
25.
Connect connector (Figure 24, Item 13) to connector (Figure 24, Item 12).
26.
Connect connector (Figure 24, Item 9) to connector (Figure 24, Item 10).
27.
Position clamp (Figure 24, Item 5) on instrument wiring harness assembly (Figure 24, Item 4).
28.
Install clamp (Figure 24, Item 5) on operator station stud (Figure 24, Item 3) with washer (Figure 24, Item 7)
and new locknut (Figure 24, Item 8).
03/15/2011Rel(1.8)root(maintwp)wpno(M00137)