TM 5-3895-379-23-1
0199
INSTALLATION
NOTE
1.
Place instrument box assembly (Figure 14, Item 13) on clean surface.
2.
Position instrument wiring harness assembly (Figure 14, Item 14) in instrument box assembly
(Figure 14, Item 13).
NOTE
Perform Steps (3) through (7) for CB534C Roller.
3.
Install washer (Figure 14, Item 10), instrument wiring harness connector (Figure 14, Item 8), and nut
(Figure 14, Item 9) to FPM meter (Figure 14, Item 12).
4.
Install washer (Figure 14, Item 7), instrument wiring harness connector (Figure 14, Item 5), and nut
(Figure 14, Item 6) to FPM meter (Figure 14, Item 12).
5.
Install washer (Figure 14, Item 4), instrument wiring harness connector (Figure 14, Item 2), and nut
(Figure 14, Item 3) to FPM meter (Figure 14, Item 12).
6.
Install washer (Figure 14, Item 16), instrument wiring harness connector (Figure 14, Item 15), and nut
(Figure 14, Item 1) to FPM meter (Figure 14, Item 12).
7.
Install lamp assembly (Figure 14, Item 11) to FPM meter (Figure 14, Item 12).
1
2
3
4
5
6
7
15
8
9
16
10
11
12
13
14
M1292SWR
Figure 14.
Instrument Wiring Harness Installation.
03/15/2011Rel(1.8)root(maintwp)wpno(M00137)