TM 5-3895-379-23-1
0199
INSTALLATION - Continued
8.
Install three new lockwashers (Figure 15, Item 3), wires (Figure 15, Items 2, 5, and 8), and screws
(Figure 15, Item 1) on starter switch assembly terminals (Figure 15, Items 4, 6, and 9).
1
2
3
4
9
1
8
3
5
1
7
6
3
M1291SWR
Figure 15. Instrument Wiring Harness Installation.
9.
Install three new lockwashers (Figure 16, Item 4), wires (Figure 16, Items 2, 3, and 5), and nuts
(Figure 16, Item 1) on fuel level indicator terminals (Figure 16, Items 6, 9, and 10).
10.
Install lamp assembly (Figure 16, Item 8) on fuel level indicator (Figure 16, Item 7).
1
3
1
2
4
1
10
4
9
5
4
6
8
7
M0340SWR
Figure 16. Instrument Wiring Harness Installation.
03/15/2011Rel(1.8)root(maintwp)wpno(M00137)