TM 5-3895-379-23-1
0211
ASSEMBLY - Continued
2.
Install new backup ring (Figure 2, Item 12), new O-ring (Figure 2, Item 11), new preformed packing
(Figure 2, Item 10), and two metering fittings (Figure 2, Item 13) on valve body (Figure 2, Item 9).
3.
Install two switches (Figure 2, Item 7) on pivot bracket (Figure 2, Item 3) with screws (Figure 2, Item 8).
4.
Install new gasket (Figure 2, Item 14), plate (Figure 2, Item 15), and pivot bracket (Figure 2, Item 3) on valve
body (Figure 2, Item 9).
5.
Install three screws (Figure 2, Item 4) and boot clamp (Figure 2, Item 5) to valve body (Figure 2, Item 9).
3
1
2
4
1
5
6
6
8
7
15
7
14
9
10
11
12
13
M1153SWR
Figure 2.
Propel and Speed Control Valve Assembly.
END OF TASK
FOLLOW-ON MAINTENANCE
END OF TASK
END OF WORK PACKAGE