TM 5-3895-379-23-1
0165
INSTALLATION - Continued
5.
Install instrument box assembly (Figure 4, Item 4) on operator station (Figure 4, Item 7) with three washers
(Figure 4, Item 6) and screws (Figure 4, Item 5).
6.
Install vandal guard (Figure 4, Item 3) on instrument box assembly (Figure 4, Item 4) with two washers
(Figure 4, Item 2) and shoulder screws (Figure 4, Item 1).
3
2
1
7
6
5
4
M0893SWR
Figure 4. Starting Aid Switch Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Close right-side door assembly. (TM 5-3895-379-10)
2.
Remove chocks. (TM 5-3895-379-10)
END OF TASK
END OF WORK PACKAGE
03/15/2011Rel(1.8)root(maintwp)wpno(M00103)