TM 5-3895-379-23-1
0154
REMOVAL
1.
Remove two screws (Figure 1, Item 1) and washers (Figure 1, Item 5) from operator station (Figure 1, Item 4).
2.
Remove seven screws (Figure 1, Item 1) and washers (Figure 1, Item 2) from operator station
(Figure 1, Item 4).
3.
Lift panel assembly (Figure 1, Item 3) and pull away from operator station (Figure 1, Item 4).
1
2
1
2
3
4
5
1
M0849SWR
Figure 1. Main Relay Removal.
4.
Disconnect main relay connector (Figure 2, Item 6) from connector (Figure 2, Item 7).
NOTE
Tag and mark all wires prior to removal.
5.
Remove two nuts (Figure 2, Item 3) and two wires (Figure 2, Items 1 and 2) from main relay
(Figure 2, Item 5).
6.
Remove two nuts (Figure 2, Item 8), washers (Figure 2, Item 9), and main relay (Figure 2, Item 5) from operator
station (Figure 2, Item 4).
03/15/2011Rel(1.8)root(maintwp)wpno(M00092)