TM 5-3895-379-23
FUSE AND FUSE HOLDER REPLACEMENT - CONTINUED
0077 00
REMOVAL - CONTINUED
3.
Remove two shoulder screws (5), washers (6) and
vandal guard (7) from instrument box assembly (8).
6
7
5
4.
Remove three screws (9) and washers (10) from oper-
ator station (11).
5.
Lift and tilt back instrument box assembly (8) to gain
access to back of instrument box assembly.
8
9
10
11
401-467
NOTE
Tag and mark all wires prior to removal.
6.
Cut two wires (12) and remove from fuse holder
assembly (2).
2
7.
Remove nut (13) from fuse holder assembly (2).
8.
Remove fuse holder assembly (2) and seal (14) from
12
instrument box assembly (8). Discard seal.
14
12
13
8
401-468
INSTALLATION
1.
Install new seal (14) on fuse holder assembly (2).
2.
Install fuse holder assembly (2) on instrument box assembly (8) with nut (13).