Figure 3. Rollover Protection Structure (ROPS) Assembly Installation
RAISE/LOWER OPERATOR PLATFORM ASSEMBLY

Technical Manual For Roller, Motorized, Vibrating Tandem Steel Drums - 2 Page Navigation
  78    79    80    81    82  83  84    85    86    87    88  
img
.
TM 5-3895-379-23-2
0234
INSTALLATION - Continued
5.
Install three handrail assemblies (Figure 4, Items 3, 6, and 7) on ROPS assembly (Figure 4, Item 4) with six
washers (Figure 4, Item 1) and bolts (Figure 4, Item 2). Turn bolts until snug, but do not tighten bolts.
6.
Install three handrail assemblies (Figure 4, Items 3, 6, and 7) on ROPS assemby (Figure 4, Item 4) and frame
assembly (Figure 4, Item 12) with three washers (Figure 4, Item 11) and bolts (Figure 4, Item 10). Tighten bolts
to 518-666 lb-ft (702-903 Nm).
7.
Tighten six bolts (Figure 4, Item 2) to 65 lb-ft (88 Nm).
8.
Install rear handrail assembly (Figure 4, Item 5) on ROPS assembly (Figure 4, Item 4) with four washers
(Figure 4, Item 9) and bolts (Figure 4, Item 8). Tighten bolts to 45 lb-ft (61 Nm).
1
2
9
8
4
5
7
3
6
4
5
7
7
10
11
12
M0741SWR
Figure 4. Rollover Protection Structure (ROPS) Assembly Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
Remove chocks. (TM 5-3895-379-10)
END OF TASK
END OF WORK PACKAGE